Zone Striping, Inc. Completes Phase 1 of a 14,500 Car Parking/Staging Area for Imported Cars
The Delaware River Port Authority, Southport Site 1 project has only one (1) bid item, that being “438,000 LF – 4” Wide Epoxy Resin Line Striping”. Where the challenge lies, is that this work consists entirely of parking stall striping. Normally, parking stall striping consists of extensive layout and installation with a “walk behind” line striper. Needless to say, 438,000 LF is nearly 83 miles of walking. Once for layout and again for installation.
The layout is a basic grid pattern and the work is “pre-marked” with string lines and marking paint. Zone’s crews installed the work entirely with a 77,000 LB GVW, 42 foot long, tri-axle, epoxy resin striping truck. No walking required!
Phase 1 consists of just over 4,000 cars and as such it required 100,000 LF of striping including over 8,000 LF of 16” long “tick marks” for car alignment. The work was completed safely, efficiently and to the full satisfaction of our customer the H&K Group (Haines and Kibblehouse) Philadelphia Division and the project Owner. Zone Striping, Inc. would like to thank its crews for their continued commitment to quality and efficiency.